What You Need to Know Before Starting a Full Home Renovation in Vancouver

Published

Renovating to stay and renovating to sell are two different projects wearing the same scope of work. That one answer is what the rest of the decisions hang off, and it comes a long way before anybody picks a finish.

The scope of a full home renovation

A full home renovation usually means taking the house back to the studs and rebuilding it to current standards. Kitchen and bathrooms, floors, insulation, wiring and plumbing, sometimes the structure, and often the roof or the siding at the same time.

That scope is what makes it the right answer for a lot of Vancouver housing stock. Opening a floorplan chopped into small rooms. Lifting a character home to put a suite underneath it. Correcting a layout that has been added to twice. None of those is room-by-room work.

The opposite case is worth saying out loud. If one room is the problem, rebuilding the whole house is an expensive way to fix it.

Permits, planning and the realities of renovating here

Renovating in Vancouver is far less a question of finishes than most people expect. A whole-house project usually needs several permits at once — building, electrical and plumbing, with a development or heritage review on top in some neighbourhoods.

The BC Building Code sets what the rebuilt house has to meet, and that is where most of the paperwork comes from. The BC Energy Step Code sits beside it, and how far it reaches depends on the scope: the Province frames both step codes around new construction, so a rebuilt storey or a new part of the house is where they bite hardest. CAS prepares the applications, submits them and carries them through to the final inspection.

The reason that matters is sequencing. An application that is complete but submitted in the wrong order still waits, and a house with its walls open is an expensive place to wait.

Renovating to stay, or renovating to sell

The first question worth answering is whether you are staying in the house or selling it. Almost every decision downstream changes with the answer.

If you are staying, the budget goes into what you feel daily. Heat that is comfortable in February. Rooms that are quiet. Storage where you actually reach for it. A kitchen built around the way you cook rather than the way kitchens photograph.

If you are selling, it goes into the work a buyer registers on the first walkthrough and an appraiser can verify. Kitchens, bathrooms, and anything that adds usable, permitted floor area.

The expensive mistake is doing half of each — a house specified for resale with one personal indulgence in the middle of it tends to satisfy nobody.

Decide whether you are renovating to stay or to sell before you decide anything else. It is the answer the rest of the project hangs off.
Honed white marble countertop edge over white oak cabinetry with a brushed nickel faucet

Where the budget actually goes

Everyone asks what it costs first. The honest answer is that scope sets the number long before finishes do. Three of the four things driving scope are discovered rather than chosen.

The four that matter most

How much of the layout changes
Removing a partition wall is modest work. Moving the kitchen, the plumbing stack or a bearing wall is a different project.
Whether the structure is touched
Underpinning, a lifted house or a new beam brings an engineer in and lengthens the permit path.
What the walls are hiding
Knob-and-tube wiring, failed waterproofing, rot behind a shower. These are found once demolition starts, not quoted beforehand.
The level the finishes are specified at
The one line you control from the first day, and the one that drifts most quietly as the job goes on.

CAS does not publish a price per square foot for a whole-house renovation. A rate that covers both a 1960s bungalow in East Van and a character home in Dunbar helps neither owner. It also tends to be quoted back later as though it had been a quote.

What is useful is a scope and a set of allowances written against your house, with the three discovered items above carrying a contingency.

On the energy side, BC runs rebate programmes for insulation, windows and heat pumps. What qualifies and what it pays out both change, so check the current terms before a rebate becomes part of the budget.

How long it takes

There is no single number, and the ranges quoted in conversation usually leave out the half of the project that happens before site work starts. These are the two durations CAS publishes and plans against.

The two ranges CAS plans against

2 to 4 months
Design, planning and permits
4 to 8 months
Construction, full home

They run back to back on most whole-house projects, and the first one is the one people underestimate. Approvals and undecided choices are what actually stall a renovation. Neither is fixed by working faster on site.

Choosing who does the work

Questions for anyone quoting on your house

CAS included. These are the answers worth having in writing before a contract is signed, from whoever you end up hiring.

Worth hearing

  • Recent work inside the City of Vancouver permit process, not a general claim of experience with permits
  • A plain explanation of what the Energy Step Code means for your particular house
  • References from projects close enough to visit
  • An estimate written line by line, with the allowances named
  • A clear answer on who is on site daily and who you call when a decision is needed

Worth worrying about

  • A contract that describes the work in general terms
  • Deflection when you ask about code, inspections or permit timing
  • No current proof of licensing, insurance or WorkSafeBC coverage
  • A price well below everyone else's, with no explanation of what is different

On a whole-house job the thing to pin down is presence. A renovation managed from a distance shows up later in the small decisions nobody was there to make, and those are the ones that are expensive to undo.

Living room with a linear gas fireplace set into a white wall and a deep sectional

The week before anyone arrives

  • Set a contingency, and decide in advance what it is allowed to pay for. An undefined buffer gets absorbed by upgrades, and then the rot behind the shower has nothing to draw on.
  • Do not compress the design phase. A decision changed on paper costs a conversation. The same decision changed on site costs the work already done.
  • Choose for the long run on anything you touch daily. The cheaper version of a tap, a hinge or a floor gets replaced, and the second time it is paid for twice.
  • Answer quickly. A choice left open holds up every trade queued behind it, and that queue is where most schedules are actually lost.

All of it happens in the week before anyone arrives, and all of it is free to settle then. That week is the cheapest part of a whole-house renovation, and the one most often skipped.